Off-System Road Rehabilitation

Project Status and News
More to come!
Allocation Priority: M2
Project Name: Off-System Road Rehabilitation
Project Type: Match – FEMA PA
HUD National Objective: Unmet Need/ Low Moderate Income
Long-Term Recovery Plan: Evacuation Routes
Project Total Cost: $45,896,875
CDBG-DR Project Grant Amount: $10,030,224
Environmental Completion Year: Complete
Design & ROW Completion Year: Complete
Construction Completion Year: 2026
Project Scope
The Off-System Road Rehabilitation Project repairs damaged sections of roadway and re-striping when necessary to rehabilitate 47 miles of roadway segments of on-system roadway. The project also upgrades non-compliant ADA curb ramps.
Project Description
The project will repair 47 miles of off-system roadways that sustained heavy damage in the wake of the Camp Fire. The critical condition of the current roadways risks pavement failure and creates unsafe road conditions. The project will improve safety along public roads that are not part of the federal-aid system. These roads include local roads and rural minor collectors, which provide evacuation routes connecting to the federal-aid system.